Being a Roadmap from now (June 2007) til end of August 2007.

Based on a meeting on May 31, (AW, BL, DL, SP)

Also covers GUI activities. (See also ticket:647 and this page).

June Aims:

  • End of Week 1:
    • WMS 0.1 based on OWS stack and CSML available. (SP, #756)
    • CSML supports QXF read writes (DL, ticket:753)
    • CSML supports XMLBASE (or equivalent) (DL, ticket:748)
  • End of Week 2:
    • CSML API Server 0.1 available (SP/DL), #758
      • This is pretty much done as far as BL is concerned
      • This is NOT pretty much done as far as SP is concerned! but progress should be fast see #758
  • Weeks 2-4:
    • WCS version investigation completed (1 day, DL, ticket:749).
    • WCS 0.1 built based on OWS stack (DL, ticket:752)
    • WPS 0.1 built based on OWS stack (SP, #757) (See also ticket:613)
    • Shopping cart available in browse (BL, ticket:742)

(Could DL and SP add appropriate tickets and link them here?)

Change History

comment:1 Changed 12 years ago by lawrence

Note we (who?) can work on the GUI based on SP's DDC code in July, before getting Stephen back in August.

comment:2 Changed 12 years ago by domlowe

  • Description modified (diff)

adding ticket link

comment:3 Changed 12 years ago by domlowe

  • Description modified (diff)

comment:4 Changed 12 years ago by domlowe

  • Description modified (diff)

comment:5 Changed 12 years ago by spascoe

  • Description modified (diff)

comment:6 Changed 12 years ago by spascoe

  • Description modified (diff)

I've extended the deadline for CSML API service because Dom and I need to talk through exactly what is required.

comment:7 Changed 12 years ago by spascoe

  • Status changed from new to assigned
  • Milestone changed from BETA+Services to PROD Step2

Reassigning to appropriate PROD milestone

comment:8 Changed 11 years ago by spascoe

  • Status changed from assigned to closed
  • Resolution set to fixed

All sub-tickets crossed. Closing ticket.