[WG] DP internal upgrade: NOCS moving server

Reported by: mggr Owned by: fvenuti
Priority: discussion Milestone:
Component: community Version:
Keywords: Cc:

Description

At the May 06 WG meeting, Fabio said they'd need to upgrade their current server (godiva?), which may have an effect on NDG. The timeframe was estimated at approximately 2 months (Aug/Sept?).

This ticket raised to track the issue/inform the WG team.

Change History

comment:1 Changed 13 years ago by fvenuti

  • Status changed from new to assigned

comment:2 Changed 13 years ago by fvenuti

Last news is that godiva will not be turned off, but OAI and security software will be moved to a new machine anyway. Estimated time for completion of porting is 01/08/2006

comment:3 Changed 13 years ago by fvenuti

The OS has been installed on the new ndg server that is now ready for a fresh installation of all ndg related applications. The transition from the current server "godiva" to the new server (in particular for what concerns OAI) will happen only when we are reasonably sure that everything works fine.

comment:4 Changed 12 years ago by fvenuti

  • Status changed from assigned to closed
  • Resolution set to fixed

Transition completed