Description
Need a short presentation which will be available based on the proposed security paper.
Change History
comment:2 Changed 15 years ago by lawrence
Looks like I'll only get this done on the plane to GO-ESSP. Is that too late for Roy?
comment:4 Changed 15 years ago by rkl
Yes and no. The SeaDataNet? TTG was last week and a few slides from Phil's existing presentation set the scene for that. At the moment the French are proposing an LDAP-based solution for authentication, but questions on how this can be used for authorisdation met with the classic Gallic shrug - basically anyone who authenticates can have it all. When pushed further they then moved to going totally open 'to get something working fast' (sigh....).
In Greece the week after next, what I have to do is get a clear agreement that role-based authorisation is what SeaDataNet? needs. It will then fall to the next TTG meeting (August/September?) to decide how this is done. Assuming I succeed in Greece, that's when an upgraded presentation would really come into its own.
comment:5 Changed 15 years ago by pjkersha
The presentation I gave for the DEWS security workshop is the most up to date version. It's on the BSCW:
http://bscw.badc.rl.ac.uk/bscw/bscw.cgi/d90636/DEWS%20Security%20Workshop.ppt
comment:6 Changed 15 years ago by lawrence
- Milestone changed from ALPHA to External Product Definition
We have something, but it still needs considerable streamlining. Can't attach here because it's too big ...
comment:7 Changed 14 years ago by selatham
Is this a Documentation_preBeta task now? Do we need anything before that?
comment:8 Changed 14 years ago by lawrence
- Milestone changed from External Product Definition to PROD
comment:10 Changed 14 years ago by selatham
- Status changed from assigned to new
- Owner changed from lawrence to pjkersha
- Milestone changed from Reporting and Futures to PROD Final
Actually, won't Phil need this for e-Science AHM in early September? Will Phil write it?
comment:11 Changed 13 years ago by pjkersha
- Status changed from new to closed
- Resolution set to fixed
Presentation was made for e-Science AHM in Sept.