Roadmap

Milestone: V3.5 UML Final

8 years late (30/04/11 00:00:00)

0%

Number of tickets:
closed:
0
active:
15
Total:
15

The next MOLES release, aims to include:

  • Support for computational observations
  • Clear stereotype/tagging to indicate information life cycle
  • Process re-use
  • Support for EOF and Gemini export

Milestone: V3 Atom Serialisation

8 years late (30/05/11 00:00:00)

0%

Number of tickets:
closed:
0
active:
5
Total:
5

We need to be able to serialise MOLES documents, and potentially documents pointed to by MOLES, as Atom documents.

Milestone: V3 Prototype Portal

8 years late (30/06/11 00:00:00)

0%

Number of tickets:
closed:
0
active:
3
Total:
3

Prototype demonstrating V3 capabilities.

Milestone: V3.X Next Release

8 years late (30/06/11 00:00:00)

This is holding milestone for the next but one release. Activities that are scheduled for V3 UML , but not able to be supported in V3.5 should be raised against(or moved to) this milestone.

Milestone: Future V4 Holding

No date set

0%

Number of tickets:
closed:
0
active:
3
Total:
3

This is a holding milestone, for future work.

Note: See TracRoadmap for help on using the roadmap.
 Trac Powered
Site hosted at the
British Atmospheric Data Centre
for the